Amazon, Omega Business Park, Warrington

Amazon, Omega Business Park, Warrington

Amazon, Omega Business Park, Warrington

PROJECT OVERVIEW

This project involved the design and construction of a new 357,000 sq ft speculative warehouse facility in zone seven of the Omega South Site.

The project was funded by LondonMetric, who successfully agreed a 15-year lease with Amazon to occupy the warehouse.

Hannan Associates provided Building Services Consultancy and BREEAM Assessment for the building shell and core.

We were very pleased to join Chetwood Architects, Doig & Smith, WSP and main contractor Bowmer & Kirkland on the project.

The building achieved a BREEAM Very Good rating.

About This Project

5

CLIENT : Miller Developments

5

ARCHITECT : Chetwood Architects

5

PROJECT VALUE : £30 million

5

CONTRACT DURATION: April 2014 - March 2017

Get in touch

15 + 6 =

Plastic Omnium, Omega Business Park, Warrington

Plastic Omnium, Omega Business Park, Warrington

Plastic Omnium, Omega Business Park, Warrington

PROJECT OVERVIEW

This project involved the design and construction of a c235,000 sq ft state of the art manufacturing facility with c21,000 sq ft two storey offices, external car parking, HGV parking and service yard for Plastic Omnium at Omega South.

Our team provided Utilities Infrastructure, Building Services Engineering & BREAM Assessment consultancy services associated with the landlord’s CAT A works and tenant enhancement CAT B works.

Air source heat pumps provided heating and comfort cooling to the office areas with sprinkler protection to NFPA standards provided to the warehouse and office areas.

Liaison with the tenant was undertaken regarding the CAT C works to ensure co-ordination of utility supplies and drainage with the intended fit-out works of the automation manufacturing machinery.

The project achieved a BREEAM Very Good rating under the BREEAM New Construction 2011 scheme.

About This Project

5

CLIENT : Miller Developments

5

ARCHITECT : Chetwood Architects

5

CONTRACT DURATION: May 2012 - December 2015

Get in touch

3 + 10 =

The Hut Group, Omega Business Park, Warrington

The Hut Group, Omega Business Park, Warrington

The Hut Group, Omega Business Park, Warrington

PROJECT OVERVIEW

The Hut Group’s premises on a 41 acre plot at Omega South supports a mixture of functions including logistics, manufacturing, and offices, plus a further 150,000 sq ft of additional expansion land.

The project involved the construction and fit out of a 650,000 sq ft production, storage and distribution facility which includes vitamin supplement production, automated and manual order processing studio and support offices.

The new premises were built to consolidate The Hut Groups four existing UK distribution units. The facility is used to satisfy both its domestic and rapidly growing international operations.

We provided Building Services Engineering Design & BREEAM Assessment services for the CAT A fit-outs to the warehouse and 17,000 sq ft two storey office building, 11,000 sq ft two storey production office and transport office with gatehouse, external car parking, HGV parking and service yard.

The building achieved a BREEAM Very Good rating under the BREEAM New Construction 2011 scheme.

Air source heat pumps provided heating and comfort cooling to the office areas with sprinkler protection provided to the warehouse and office areas.

About This Project

5

CLIENT : Miller Developments

5

ARCHITECT : Chetwood Architects

5

PROJECT VALUE : £32 million

5

CONTRACT DURATION: May 2012 - December 2014

Get in touch

9 + 11 =

Domino’s, Omega Business Park, Warrington

Domino’s, Omega Business Park, Warrington

Domino’s, Omega Business Park, Warrington

PROJECT OVERVIEW

Located at the south side of the Omega Business Park the facility for Dominos Pizza is a 117,000 sqft industrial building, consisting of a 11,141sq.ft GIA two storey office area,  a gatehouse building constructed on a secured enclosed site, external car parking, HGV parking, and a service yard.

The building operates 24 hours a day, 7 days a week. The site and associated buildings were constructed to Cat B level of services, tailored to meet the specific needs of the building Tenant.

Our duties included producing the MEP Stage 3a Developed Design for the Cat A & Cat B Works and for Domino’s enhanced Cat B office and plant area fit-out, in preparation of the full Cat C manufacturing, storage and distribution plant fit-out to the warehouse.

Additional duties included undertaking the BREEAM Assessment and the monitoring of the MEP design contractors technical design solutions, construction works on site, and final testing and inspections for handover of the works to the Cat C fit-out contractors.

The project achieved a BREEAM Very Good rating.

About This Project

5

CLIENT : Omega Warrington Ltd

5

ARCHITECT : Chetwood Architects

5

CONTRACT DURATION: November 2015 – August 2017

Get in touch

1 + 13 =

Amazon, Logic Leeds Business Park

Amazon, Logic Leeds Business Park

Amazon, Logic Leeds Business Park

PROJECT OVERVIEW

We provided utilities infrastructure master planning and procurement for the overall development proposals and design and monitoring services for the MEP associated with the initial speculative 80,000 ft² industrial unit. As part of the team we contributed to the specification of the unit which was developed to provide a wide tenant appeal and a high level of flexibility to attract potential tenants.

The unit is now let to Amazon and we assisted the client during the letting of the unit and carried out the design and monitoring of additional car parking facilities requesting by Amazon.

Logic Leeds is part of the Leeds Enterprise Zone, which means that it benefits from a range of incentives for occupiers. Overall there is outline planning for 1.6 million ft² of quality industrial, storage and distribution development. All buildings will have a high BREEAM rating and state-of-the-art facilities.

About This Project

5

CLIENT : Muse Developments

5

ARCHITECT : Fletcher Rae Architects

5

PROJECT VALUE : £5 million

5

CONTRACT DURATION: April 2014 – May 2016