One Angel Square, Manchester

One Angel Square, Manchester

One Angel Square, Manchester

PROJECT OVERVIEW

Hannans are very pleased to have been part of the team who designed the MEP Services for the 320,000 sq ft Co-operative Group Headquarters building – One Angel Square. 

Opened by the Queen on 14th November 2013, the new head office at One Angel Square Manchester was at the time officially the world’s greenest office building, with a BREEAM score of 95.16% – ‘Outstanding.’

The design of the building was driven by the Co-operative Group’s desire to create a Carbon Negative building. The sixteen storey office building was designed to achieve a BREEAM Outstanding rating, as well as an EPC ‘A’ rated near zero carbon building, with cutting edge integrated design.

The services design included 3D modelling, together with building modelling and dynamic simulation to calculate and assess the buildings energy consumption and potential EPC and DEC ratings.

The project has won numerous honors including both Design & Innovation, and Overall Project of the Year at the 2013 RICS Awards, BCO 2013 Corporate workplace of the year, Property Week 2012 Sustainability Achievement Award, and a 2013 BREEAM Award.

About This Project

5

CLIENT : The Co-Operative Group

5

ARCHITECT : 3D Reid

5

PROJECT VALUE : £100 million

5

CONTRACT DURATION: 2009 - 2013

Ian Joyce

Ian Joyce

Director

Email: [email protected]
Phone: +44(0)161 337 2200
Awards

2011

Considerate Constructors Scheme Gold Award Builder & Engineer Awards Sustainable Project of the Year

2012

Green Apple Awards Bronze Award Property Week Awards Sustainable Achievement Award World Architecture Festival Future Project Office Shortlisted

2013

BREEAM Awards Best Office Building MIPIM Awards Best Office and Business Development National RICS Awards Project of the year National RICS Awards Design & Innovation award BCO Awards Coperate Workplace of the Year Manchester Society of Architects Awards Winner

Get in touch

9 + 4 =

Wolves FC Molineux Stadium

Wolves FC Molineux Stadium

Wolves FC Molineux Stadium

PROJECT OVERVIEW

Hannan Associates were the Building Services Designers for the master planning and redevelopment of the Molineux stadium. The first phase of the project was the new North stand, starting with the master planning of redeveloping the ground in a phased manner, with due consideration of the live stadium and site wide services. These included IT, public address, HV infrastructure, turnstile monitoring, essential services, AV systems, CCTV and replacing UEFA class 4 Elite standard sports lighting temporarily and permanently. The second phase being the new East stand, with other stands to follow. Scheme development of phase 2 including enabling works and fitting out for East stand, executive boxes, lounges and banqueting hall. Including designing services to allow early occupation of terrace and lower concourse.

About This Project

5

CLIENT : Wolverhampton Wanderers FC

5

ARCHITECT : AFL Architects

5

PROJECT VALUE : £40 million

5

CONTRACT DURATION: Aug 2009 – Sep 2011

Get in touch

14 + 7 =

Whiteknights Campus, Reading

Whiteknights Campus, Reading

Whiteknights Campus, Reading

PROJECT OVERVIEW

The University of Reading enlisted our help with de-commissioning part of a 1960’s built research faculty at their Whiteknights campus. As well as designing the refurbishment of the basement, ground and first floors, duties also included a survey of the existing structure which brought about the recognition of high levels of asbestos. All works were carried out whilst retaining the existing services and infrastructure to the Bio-science lab, science museum, refectory, lower floors, roof area and all fire escapes.

About This Project

5

CLIENT : University of Reading

5

ARCHITECT : ACR

5

PROJECT VALUE : £800,000

5

CONTRACT DURATION: 2008 – 2009

Get in touch

10 + 8 =

West Cheshire College, Ellesmere Port

West Cheshire College, Ellesmere Port

West Cheshire College, Ellesmere Port

PROJECT OVERVIEW

Our duties involved the construction of a new nursery block, the refurbishment and expansion of an existing arts block, demolition of existing teaching buildings, construction of a new teaching building, and renewal of the site utilities infrastructure. The project was centred on a fixed budget and space requirement, with very tight deadlines that has to adhere to secure funding. Speed of response by the team as a whole and value engineering were a very important aspect of the project. Natural ventilation with minimum mechanical assistance where necessary was a major feature of the design.

About This Project

5

CLIENT : West Cheshire College

5

ARCHITECT : Bond Bryan Architects

5

PROJECT VALUE : Approximately £6.0M.

5

CONTRACT DURATION: Mar 2003 – Dec 2004

Get in touch

3 + 14 =

Vision Tameside, Manchester

Vision Tameside, Manchester

Vision Tameside, Manchester

PROJECT OVERVIEW

We are very pleased to have been a part of the team who delivered Phase 2 of the ‘Vision Tameside’ master plan set to transform Ashton Town Centre. We have been undertaking the detailed design of the MEP Services and Infrastructure, as part of which we are assisting the Council with their environmental services strategy to help them meet their aspirations to create a sustainable building.

The Tameside One development includes a new Advanced Skills Centre for Tameside College alongside a new Joint Service Centre for the Council and others partners.

The 7,000sqm Advanced Skills Centre provides a new learning and skills centre for students studying vocational subjects including: hair and beauty, hospitality and catering, bakery and confectionery, travel and tourism and business skills.

The 6,000sqm Joint Service Centre incorporates a library, customer service centre, committee and training rooms and office accommodation for the Council and partners.

This phase of the development also includes a 2,150sq.m retail space for a Wilko’s store.

 

Photos by Agent Marketing

 

Tameside One Complete

 

About This Project

5

CLIENT : Tameside Council and Robertson

5

ARCHITECT : Ryder

5

PROJECT VALUE : £36 million

5

CONTRACT DURATION: 2014 – 2019

Get in touch