Ralli Quays, Salford

Ralli Quays, Salford

Ralli Quays, Salford

PROJECT OVERVIEW

Hannan Associates are part of Legal & General Investment Management’s team for the design of the Ralli Quays office and hotel scheme on the River Irwell in Salford.

The client is targeting net zero carbon via a combination of the UKGBC 2030 targets and carbon offset for both construction and operation, including a high NABERS Star Energy Rating.

The building is also targeting BREEAM excellent and EPC A.

Our role on the project includes:

  • Sustainability Services
  • BREEAM 
  • MEP Design

Ralli Quays is one of only fourteen developments in the UK pioneering the Better Buildings Partnership Design for Performance initiative.  The key objective of the Pilot Programme was to provide a strong evidence base for proceeding to a fully-fledged DfP Scheme.

As part of our package we are utilising complex thermal modelling software to accurately simulate HVAC plant and control networks for each building in order to ascertain the predicted in use operational energy consumptions for a variety of on-axis and off-axis scenarios. This is vital in providing a building-integrated approach where the HVAC systems and building are assessed as a whole all gains/losses, heat transfer and thermal mass in the building to be accounted for alongside system performance.

This allows us to address the performance gap that has been created by the out of date methodology to design buildings for compliance, as we can accurately assess the results of simulations and check against the latest Energy Performance Targets based on the Australian NABERS approach.

We are very pleased to join EPR Architects, DPP One, Turner & Townsend, Walker Sime, Clancy Consulting, Colliers on the project design team.

About This Project

5

CLIENT : Legal & General

5

ARCHITECT : EPR Architects

5

CONTRACT DURATION: October 2018 - ongoing

Get in touch

5 + 12 =

Hermes, Omega Business Park, Warrington

Hermes, Omega Business Park, Warrington

Hermes, Omega Business Park, Warrington

PROJECT OVERVIEW

This project involved the construction and fit out of a c150,000 sq ft cross dock automated parcel sorting facility for Hermes at plot 1A, Omega North, Warrington.

The building includes office accommodation, a vehicle maintenance unit, a warehousing facility, and two gatehouses. The site area is 18.43 acres with the provision of 275 car parking spaces and 262 HGV parking spaces.

Our services included Building Services Engineering, BREEAM Assessment and Utilities Infrastructure Consultancy services associated with the landlords CAT A works and tenant enhancement CAT B works for the construction and fit out of a c150,000 sq ft cross dock automated parcel sorting facility with c16,000 sq ft two storey offices, external car parking, HGV parking, service yard, fuel storage & filling point and vehicle wash.

Warehouse heating was provided via gas-fired radiant heating with gas fired boiler plant serving radiators within the office area.

Liaison with the tenant was undertaken regarding the proposed CAT C works to ensure co-ordination of the power and water supplies, drainage etc for the intended fit-out works of the automated parcel sorting machinery.

The building achieved a BREEAM Very Good rating under the BREEAM New Construction 2011 scheme.

About This Project

5

CLIENT : Miller Developments

5

ARCHITECT : Chetwood Architects

5

PROJECT VALUE : £14.5 million

5

CONTRACT DURATION: May 2012 - April 2014