Weston M6, Crewe

PROJECT OVERVIEW

Hannans are providing building services engineering consultancy for Weston M6 in Crewe.

The new state-of-the-art commercial and business park is being brought forward in two phases.

The scheme received hybrid planning permission in 2024 and has now progressed into the enabling and infrastructure works phase, with new estate roads, utilities, drainage and a 26-acre biodiversity habitat being delivered by Luddon Construction as the first stage of delivery.

Phase 1 – acquired by Hillwood UK, will deliver three high-quality logistics and industrial buildings of 148,000 sq ft, 405,000 sq ft and 200,000 sq ft.

Phase 2 – outline planning is in place for up to 575,000 sq ft of build to suit industrial and logistics spaces and offices.

As a part of our role Hannans are providing:

o Building services design

o Part L compliance assessments

o Utilities infrastructure masterplanning

o BREEAM assessor duties

o Operational Energy Modelling

Each of the units are targeting an A-rated EPC, are designed to achieve a BREEAM rating of ‘Excellent’ and will be provided with electric vehicle charge points and dedicated roof space for PV array.

We are very pleased to be working alongside AEW Architects, CW Studio, Quartz Projects Services and Integra Consulting on the project design team.

The site is situated between the A500 and David Whitby Way in the emerging Basford East neighbourhood. Once completed the scheme is anticipated to create 2,9000 new jobs.

 

About This Project

5

CLIENT : Muse & Hillwood UK

5

ARCHITECT : AEW Architects

5

CONTRACT DURATION: 2020 - ongoing

Jamie Hall

Jamie Hall

Director

Email: [email protected]
Phone: +44(0)161 337 2200

Get in touch

6 + 2 =

Pin It on Pinterest